You are here: Home Timeline

Timeline

2009 Schedule

  • December
    (planned) First grant funding solicitation awards to be announced.

  • November
    Second grant funding solicitation released November 4, 2009.
    Pre-proposal webinar held November 18, 2009.
    First Program Strategy Workshop held November 18, 2009.
    Proposals due January 13, 2010 February 16, 2010.

  • October
    Draft second grant funding solicitation comments due October 12, 2009.

  • September
    First grant funding solicitations under review.
    Request for comments issued for draft second grant funding solicitation.


  • August
    First grant funding solicitation proposals submitted.


  • July
    First funding solicitation posted on July 8th.

    Pre-proposal webinar scheduled for July 23rd.
    Proposals due August 24th.
    Awards expected to be made in December.
  • June
    First draft solicitation available for public review and comment, to be followed by release of first grant solicitation in early summer.


  • May
    Draft grant solicitation submitted for internal review.


  • March - April
    Project team conducts research on potential targets and partners for collaboration and for solar RD&D.


  • February
    RD&D program workplan approved.

Background

  • September 2006
    Passage of SB1, the "Million Solar Roofs" bill that created the California Solar Initiative Solar Research, Development, and Deployment (RD&D) program.


  • January 2007
    California Solar Initiative begins.


  • June 2008
    Request for proposals to manage the RD&D.


  • September 2008
    California Public Utilities Commission awards RD&D management contract to Itron, Inc.


  • November 2008
    Final management contract signed
    .